| Milestone Schedule |
| ================== |
| |
| On a six week cadence aligned with Chromium, Skia cuts milestone branches. |
| Clients wishing to stay on a relatively stable level of Skia often utilize these |
| branches. |
| |
| On the branch date, a healthy level of Skia near HEAD is chosen. After this |
| point, for the next six weeks, only high priority fixes are checked into the branch. |
| After the six week period, when another branch is cut, only critical (typically |
| security) fixes will be committed to any previous branch. |
| |
| Skia 2016 schedule: |
| |
| Milestone | Branch Date (end of day) |
| ----------|------------------------- |
| 50 | 02/25/16 |
| 51 | 04/07/16 |
| 52 | 05/19/16 |
| 53 | 06/30/16 |
| 54 | 08/25/16 |
| 55 | 10/06/16 |
| 56 | 11/17/16 |
| |
| The current milestone is included in the headers in |
| [SkMilestone.h](https://skia.googlesource.com/skia/+/master/include/core/SkMilestone.h). |